§38-2-7. Necessity and period for perfecting lien.
But the lien created and authorized by section one of this
article shall be discharged from and after one hundred days from
the completion of the contract and the lien created and authorized
by section two of this article shall be discharged from and after
one hundred days from the completion of the subcontract and the
lien created and authorized by section three of this article shall
be discharged from and after one hundred days from the furnishing
of the last of the materials, machinery or other supplies and
equipment and the lien created and authorized by section four of
this article shall be discharged from and after one hundred days
from the date of the furnishing of the last of the materials,
machinery or other equipment or supplies and the lien created and
authorized by section five of this article shall be discharged from
and after one hundred days from the date of the performing of the
last of the work and labor and the lien created and authorized by
section six of this article shall be discharged from and after one
hundred days from the date of the performing of the last of the
work and labor, unless, within the respective periods, the claimant
of any such lien shall have perfected and preserved the same, as
hereinafter provided in this article.