WEST VIRGINIA CODE
WVC 38 - 2 - 18
§38-2-18. Priority as among mechanics' lienors.
Of the persons acquiring liens by virtue of this article and
solely for determining priorities as among such persons,
laborers, artisans, mechanics, workmen and furnishers of
material, machinery and other necessary equipment, shall have
first liens, and the lien of such persons, when perfected and
preserved as required by this article, shall take precedence over
any lien taken or to be taken by the contractor or subcontractor
indebted to them for labor, material, machinery or other
equipment, to the extent of the amount of the lien of such
contractor or subcontractor, and the lien of a subcontractor
shall take precedence over any lien taken or to be taken by a
contractor indebted to him upon his subcontract, to the extent of
the amount of the lien of such contractor, and every assignment
or transfer by any such head contractor of his contract with the
owner or by any such subcontractor of his contract with the
contractor, or any proceeding in attachment or otherwise against
such head contractor or subcontractor, with the purpose of
encumbering or subjecting his interest in such contract, shall be
subject and subordinate to the liens of all such subcontractors,
laborers, workmen, artisans, materialmen and furnishers of
machinery and other necessary equipment who shall perfect their
liens according to the provisions of this article. But all of
such perfected liens of such laborers and workmen and of such
materialmen and furnishers of machinery and of such contractors
and subcontractors, respectively, shall be of equal dignity
without priority among themselves, except as otherwise provided in this article.
Note: WV Code updated with legislation passed through the 2012 1st Special Session