OPINION ISSUED JULY 19, 2000
CHARLES SCHRADER AND HAZEL SCHRADER
VS.
DIVISION OF HIGHWAYS
(CC-97-58)

Phillip C. Monroe, Attorney at Law, for claimants.

Andrew F. Tarr & Xueyan Zhang, Attorneys at Law, for
respondent.
BAKER, JUDGE:

Claimants brought this action for damage sustained to their
real property from a landslide allegedly
caused by the negligent maintenance of the drainage system on U.
S. Route 19. U. S. Route 19 is a road maintained by respondent in
Marion County. The Court is of the opinion to deny this claim for
the reasons more fully set forth below.

In 1964 claimants purchased their residence which is situated
approximately thirty feet below the road surface of U. S. Route 19,
near Fairmont. U. S. Route 19 is a priority road that generally
traverses in a north-south direction, but at this location the road
traverses east-west. The West Fork River, which flows from the
west to the east, is located about forty-five feet below claimants'
residence. The residence was originally built during the 1950's.
In 1971, a bedroom was added to the residence. In 1991, claimants
installed a septic tank behind their residence between the
residence and the West Fork River. A garage, which was built about
twenty to twenty-two years ago, is located on the east side of
their residence. After a set of steps in front of the residence
was washed away by water, claimants built a set of concrete steps
in front of the house on the east side of the residence. The steps
start at road level and proceed to the bottom corner of the garage.
On the west side of the property, there is an eight by ten foot
building that was constructed about fifteen to eighteen years ago.
Also, claimants installed guardrail in front of their residence
after a vehicle being driven by an intoxicated driver crashed into
their residence.

According to claimants' son, Jeffrey Schrader, a flood
occurred in 1985.
The Court takes official notice of the fact
that in 1985 heavy rainfall produced tremendous flooding in the
area in question. The West Fork River flooded above its bank to
the extent that water was above the twelve feet difference in
elevation from the river level to the foundation of the residence
and flooded the basement of the Schrader's residence. The flood
did not cause any structural damage to the residence, but flood
waters in the basement caused minor damage.

During the late 1980's, claimants began to experience
considerable water run-off from U. S. Route 19. Jeffrey Schrader
testified that the water appeared to resemble a "river coming down our front steps," causing an accumulation of three to four inches
of water in their front yard. After this water run-off began,
claimants began to notice that the road surface was cracking and
then it began sinking in one particular spot to a depth of about
six to eight inches.

In 1993, claimants began to notice problems in the basement of
their home. The basement wall on the north side of the house which
faces U.S. Route 19 began to bulge toward the inside of the
basement and cracks began to develop across the whole wall. The
residence, which does not have guttering or down spouts, has had to
have major repairs on two separate occasions.

In 1994, claimants determined that the wall on the north side
of the residence facing the road was in a such a state of disrepair
that they were required to rebuild the wall. This repair project
took about two months to complete and cost approximately
$10,000.00. Then in 1996, claimants were forced to undertake a
second major construction project in an attempt to save their home
from being pushed completely off its foundation. To accomplish
this project, claimants' residence was placed on stilts and all
four walls along with the foundation were rebuilt. Claimants also
had a foundation constructed for the storage building located to
the west of the residence. This project took about three months to
complete at cost of approximately $33,000.00.

Claimants contend that during the time beginning in 1989 or
1990 when the damage to their residence was occurring, they made
telephone calls to respondent, wrote letters, and personally
contacted respondent on several occasions, but respondent did not
take corrective measures until 1996. Jeffrey Schrader testified
that the drainage system on the opposite side of U. S. Route 19
does not function properly and he personally noticed water ponding
on both sides of the road in the summer of 1998. After the
retaining wall was constructed by respondent in 1996, Mr. Schrader
dug a small drainage ditch on his property. This drainage ditch,
about thirty feet from the residence, provides a path for the water
to flow from the road into the West Fork River. Claimants are
continuing to experience cracks in the basement on the west wall of
their residence.

Along U. S. Route 19, across the road from the Schrader
residence on the north side, there is a ditch from which the water
flows into a culvert beneath the surface of the road. This culvert
continues beneath claimants' driveway for one-hundred fifty to two
hundred feet. Then the culvert and drain proceed down to the river
bank. The ditch and culverts were installed by a contractor at the
direction of respondent. In accordance with the terms of a 1996
contract with respondent, the contractor on the projects was
required to clean the culverts on the road to alleviate a standing
water problem. Claimants contend that this drain has been the
source of the problems which have occurred to their residence.

The position of respondent is that it has not been negligent
in the maintenance of the ditch line on U. S. Route 19. In 1991, the road was determined to be in a state of disrepair. When
respondent discovered the condition of its roadway, it placed hot
patch on the road surface. In1996, the road was repaved and
respondent installed a retaining wall. The retaining wall consists
of a whaler across the top of the frame with lagging between
vertical piles which are anchored into the rock beneath the ground
level about twenty-five feet.
"Lagging" is material, usually timber
or steel, that is placed between or behind the flanges of the piles
in order to hold material that is secured. According to Marion
County Crew Chief, Howard Swidler, the culverts are checked when
necessary and these culverts were checked after 1996 and appeared
to be "wide open, clean as a whistle." However, Mr. Swidler
admitted that he did not personally check the culverts because he
did not believe there was a problem. Both Mr. Swidler and Marion
County Foreman, Bill Ray Lane, testified that they were aware of
flooding problems in the area that were caused by the river about
one mile farther along the road. Both testified that the river, on
occasion, flooded and required the road to be closed to the west of
claimants' property.

Dr. Lyle K. Moulton, claimant's geotechnical expert in soils
and foundations, examined claimants' property on four occasions
from November 1997 - February 1999. It is his opinion that
respondent has not responded properly to the cause of the landslide
which affects not only claimants' property but also U.S. Route19.
Dr. Moulton testified that the particular slide involved in this
claim probably has existed since the late 1980's, but he was unable
to identify what originally caused the landslide. He is of the
opinion that this slide is progressive in nature, meaning that it
begins at the top above the road and is progressing down the slope
toward the West Fork River with claimants' property between the
road and the river. When respondent constructed the retaining wall
in 1996, it addressed the landslide only as far as U.S. Route 19 is
concerned. There is now a crack in the ground in front of the
retaining wall which is approximately one and a half inches wide
and twelve feet long. This crack proceeds through the property to
the south of the retaining wall. In his opinion this is evidence
of the slip plane where the residual sliding is taking place all
the way to the river. Dr. Moulton suspects that water is flowing
horizontally under the roadway, from the side farthest away from
claimants' residence from an undetermined source toward their
property, removing granular material beneath the surface of the
road thus causing the road to fall and collapse. He noted that the
road is giving way and must be patched with asphalt where it is
sinking. The timber lagging does not go all the way down, so rock
used behind the wall on one side works its way out from under the
lagging on the top. The fill material between the road and the
retaining wall is falling down the slope at the top of claimants'
property. Dr. Moulton is of the opinion that respondent should
have anticipated that this landslide would continue to cause
problems farther down the slope affecting the stability of claimants' property.

Further, Dr. Moulton testified that the landslide area was
aggravated by respondent's road work. The continued resurfacing of
the pavement added a substantial thickness of material, which has
a substantially higher unit weight than the soil itself. The
existing limiting equilibrium system was aggravated by respondent's
maintenance of the road when it added more weight to the top of the
slope by resurfacing the roadway, which caused further movement in
the slope. A stability analysis performed by Dr. Moulton indicates
that this situation took place over such a long period of time that
there was sufficient movement in the slope so that the residual
strength of the soil was mobilized.
A "stability analysis,"
also known as a "Bishop analysis," is a computer program that tries
to determine the critical center circle that would produce the
lowest factor of safety, which would be indicated by a value of
"1." This process is done by repeating the analysis many times,
moving the center around and calculating the factor of safety for
any circle through a particular point. The computer program keeps
resolving the problem until it finds the lowest factor of safety,
which is the minimum factor of safety for the particular analysis.
Eventually ths program establishes where a landslide is occurring.
Since the weight of the road probably exceeded the peak strength,
Dr. Moulton believes that the analysis shifted to residual
strength.
"Peak strength" is when the soil is loaded up, there is
a stress strain response where the shear stress develops to a
certain peak level. As the deformation continues it levels out,
which leave the "residual strength," which can be substantially
below the peak strength. Dr. Moulton believed that data from 1998
to February 1999 establish that the slide begins in the middle of
U. S. Route 19 and proceeds to below the toe of the slip which is
in the West Fork River. Additionally, Dr. Moulton was of the
opinion that traffic proceeding over the road was another
significant factor affecting the landslide.

Dr. Moulton rejected Dr. George A. Hall's , a geotechnical
engineer employed by respondent, expert opinion that the landslide
is a retrogressive slide and began at the toe of the slope. Dr.
Moulton asserts that his observations of the river did not indicate
that the landslide starts from the bottom of the slope, rather it
began at the top of the slope above the road. During his on site
visits to the Schraders' property, Dr. Moulton observed cracks in
claimants' residence proceeding down the slope. The basement wall
has moved outward, but there is not much movement in the vertical
face of the south wall. While the cracks on the residence appeared
before the tension cracks, Dr. Moulton believed that the
residence's foundation, during construction, may have been the
cause. Except for the tension cracks at the top of the road, there
were no other scarps or clear signs of a step-wise failure. If the
landslide is a retrogressive slide, Dr. Moulton is of the opinion
that it would have affected claimants' residence before affecting
the road. However, Dr. Moulton indicated that the road, not the Schrader residence, was affected. Further, Dr. Moulton asserts
that Dr. Hall's failure to depict the river level explained the
destabilizing effect obtained by Dr. Hall's stability analysis.
All of the factors considered by Dr. Moulton led him to the
conclusion that there was a progressive slide beginning at the road
and moving toward the river bank. As this slide moves, it is
causing the damages to claimants' property and residence.

Dr. Hall is of the opinion that the landslide which is causing
the damage to claimants' property and to respondent's road (U.S.
Route 19) begins at the bottom of the slope. According to Dr.
Hall, this slide apparently started in the mid-1980's and moved its
way up the slope through claimants' property to U.S Route 19. This
particular slide is thus retrogressive in nature rather than
progressive, i.e., the slide is moving up the slope rather than
down the slope as is the usual scenario for slides. Dr. Hall
asserts that Dr. Moulton admits that the peak strength of the soil
would have existed before there was a landslide at that location.
According to Dr. Hall, this admission supports his theory that the
only place for a failure to occur was at the bottom of the slope.
Using a stability analysis utilizing residual strength, Dr. Hall
observed that there was no failure once the slip plane formed all
the way to the road.

There was a lot of water pressure from the 1985 flood which
would have saturated that slope. Dr. Hall calculated the water
level of the river to be twenty feet higher than the water level
was prior to the flood. Dr. Hall opined that the water pressure and
velocity from the higher water level would have been sufficient to
cause ground erosion in the river bank. With the erosion and
saturation of the soil in the lower part of the slope, when the
river went back down a failure in the lower part of the slope was
initiated. This condition, which eventually created a scarp, was
not a total failure but it reached peak strength and probably
exceeded it slightly, which allowed that material to move and
remove support from the above material. At the time the piling was
installed for the retaining wall, the water table was almost at the
ground surface. Dr. Hall explained that additional water is coming
from a previous mine, a coal seam or some typical stratum that puts
water into the ground, which is a natural condition. The septic
tank, added by claimants to their property in 1991, further
saturated the soil with approximately one-hundred-fifty gallons of
water per day. At this point, the slippery clay-silt soil at the
toe of the slope became lubricated which led to the retrogressive
failure and the slide which eventually moved up toward the road.
Likewise, Dr. Hall observed a current residual failure in the
slope, which he believes substantiates his opinion that this is a
retrogressive slide with the failure starting at the bottom of the
slope. Dr. Hall further testified that he did not include the
river in the stability analysis because that is where the water
level was at the time of the investigation.

Dr. Hall testified that an important difference between his and Dr. Moulton's expert opinions regards a scarp on the Schrader
property. Dr. Moulton believes a scarp is a necessary sign of a
retrogressive slide, while Dr. Hall believes that a scarp is not a
necessary sign for a retrogressive slide. According to Dr. Hall,
when the soil below pulls away, there is some tension and the soil
can expand. Cracks and deformations can develop in the soil. In
the bottom portion of the slip, the material is being pushed and
compressed. If material at the bottom moves and the support is
removed at the bottom, then the slip can move further up the slope.
Then, when there is a crack above, this moves slightly down the
slope, removing support from material further up the slope and the
landslide continues to progress further up slope with each step,
creating what Dr. Hall described as a "domino effect." If pressure
is reduced, resistance is reduced for the next block of material,
and the effect continues. Thus, a scarp is not necessary and is a
matter of pressure between the different pieces of the eventual
slide. He provided evidence of this opinion in photographs of the
ground surface on the south side of claimant's property near the
West Fork River which revealed small cracks in the soil.
Additionally, Dr. Hall disagrees with Dr. Moulton that the
patching placed by respondent on U.S. Route 19 aggravated the
landslide. Dr. Hall is of the opinion that the pavement
irregularities developed after the cracks formed south of the
retaining wall creating a material void and causing the material
from behind the piling to fall through the timber, thus pulling
soil from beneath the road surface and causing the pavement to
sink. Accordingly, it is his opinion that a retrogressive slide
beginning below claimants' residence at the West Fork River is the
proximate cause of the damage that has occurred and it is the cause
of the continuing damage to claimants' residence and property.

The Court has held that respondent has a duty to provide
adequate drainage of surface water, and drainage devices must be
maintained in a reasonable state of repair. Haught vs. Dept. of
Highways, 13 Ct. Cl. 237 (1980). In claims of this nature, the
Court will examine whether respondent negligently failed to protect
a claimant's property from foreseeable damage. Rogers vs. Div. of
Highways, 21 Ct. Cl. 97 (1996). In the claim of Mount v. DOH,
OPINION ISSUED January 28, 2000, this Court held that respondent
was responsible for a slide occurring on claimant's property when
it continually placed asphalt on the road above claimant's property
without regard to the effect of the additional weight on the soil
beneath the road surface. Although the slide was progressing from
above the road, the weight of the road caused the slide to progress
further below the road, causing damage to claimant's property.
Maintenance of the drainage ditch adjacent to the road allowed
water to saturate the soil thus providing a slip plane for the
slide. The claim herein presents a case of first impression for
this Court as one of the experts is of the opinion that the
proximate cause of the damage to claimants' property is the result
of a retrogressive slide. This Court has not had a claim of that nature prior to the instant claim. However, after due
consideration of the testimony of both experts, the Court has
reached the conclusion that the evidence herein does make a case
for a retrogressive slide rather than a progressive slide. The
fact that there is evidence of cracking in the soil at and near the
West Fork River; that the south basement wall of the house is
beginning to fail again; the slope is elongating as the toe of the
landslide is moving faster than the head of the landslide; and that
there is evidence of the soil cracking at the south edge of the
retaining wall all seem to the Court to substantiate the theory put
forth by Dr. George Hall that this is in fact a retrogressive
slide. It is an unusual phenomenon but the Court is of the opinion
that Dr. Hall is correct in his analysis of the situation herein.

Further, the Court is of the opinion that respondent, once on
notice of the situation on U. S. Route 19, took immediate and
reasonable action to prevent any further drainage onto claimants'
property from the landslide and excess water flowing across the
road onto their property. The Court finds that the terrain in this
area of U. S. Route 19 is typical of many areas in West Virginia
which are subject to landslides. In the instant claim, claimants
have failed to established that respondent maintained U. S. Route
19, in Marion County, in a negligent manner. While the Court is
sympathetic to the situation of claimants, the fact remains that
there are many factors which have brought about this particular
landslide problem affecting their property, including the unusually
high water in 1985, the natural drainage area and the location of
the residence. Consequently, there is insufficient evidence of
negligence on the part of respondent upon which to base an award.

In accordance with the finding of facts and conclusions of law
stated herein above, the Court is of the opinion to and does deny
this claim.

Claim disallowed.
__________________
OPINION ISSUED January 28, 2000, this Court held that respondent
was responsible for a slide occurring on claimant's property when
it continually placed asphalt on the road above claimant's property
without regard to the effect of the additional weight on the soil
beneath the road surface. Although the slide was progressing from
above the road, the weight of the road caused the slide to progress
further below the road, causing damage to claimant's property.
Maintenance of the drainage ditch adjacent to the road allowed
water to saturate the soil thus providing a slip plane for the
slide. The claim herein presents a case of first impression for
this Court as one of the experts is of the opinion that the
proximate cause of the damage to claimants' property is the result
of a retrogressive slide. This Court has not had a claim of that
nature prior to the instant claim. However, after due
consideration of the testimony of both experts, the Court has reached the conclusion that the evidence herein does make a case
for a retrogressive slide rather than a progressive slide. The
fact that there is evidence of cracking in the soil at and near the
West Fork River; that the south basement wall of the house is
beginning to fail again; the slope is elongating as the toe of the
landslide is moving faster than the head of the landslide; and that
there is evidence of the soil cracking at the south edge of the
retaining wall all seem to the Court to substantiate the theory put
forth by Dr. George Hall that this is in fact a retrogressive
slide. It is an unusual phenomenon but the Court is of the opinion
that Dr. Hall is correct in his analysis of the situation herein.

Further, the Court is of the opinion that respondent, once on
notice of the situation on U. S. Route 19, took immediate and
reasonable action to prevent any further drainage onto claimants'
property from the landslide and excess water flowing across the
road onto their property. The Court finds that the terrain in this
area of U. S. Route 19 is typical of many areas in West Virginia
which are subject to landslides. In the instant claim, claimants
have failed to established that respondent maintained U. S. Route
19, in Marion County, in a negligent manner. While the Court is
sympathetic to the situation of claimants, the fact remains that
there are many factors which have brought about this particular
landslide problem affecting their property, including the unusually
high water in 1985, the natural drainage area and the location of
the residence. Consequently, there is insufficient evidence of
negligence on the part of respondent upon which to base an award.

In accordance with the finding of facts and conclusions of law
stated herein above, the Court is of the opinion to and does deny
this claim.

Claim disallowed.
__________________
OPINION ISSUED January 28, 2000, this Court held that respondent
was responsible for a slide occurring on claimant's property when
it continually placed asphalt on the road above claimant's property
without regard to the effect of the additional weight on the soil
beneath the road surface. Although the slide was progressing from
above the road, the weight of the road caused the slide to progress
further below the road, causing damage to claimant's property.
Maintenance of the drainage ditch adjacent to the road allowed
water to saturate the soil thus providing a slip plane for the
slide. The claim herein presents a case of first impression for
this Court as one of the experts is of the opinion that the
proximate cause of the damage to claimants' property is the result
of a retrogressive slide. This Court has not had a claim of that
nature prior to the instant claim. However, after due
consideration of the testimony of both experts, the Court has
reached the conclusion that the evidence herein does make a case
for a retrogressive slide rather than a progressive slide. The fact that there is evidence of cracking in the soil at and near the
West Fork River; that the south basement wall of the house is
beginning to fail again; the slope is elongating as the toe of the
landslide is moving faster than the head of the landslide; and that
there is evidence of the soil cracking at the south edge of the
retaining wall all seem to the Court to substantiate the theory put
forth by Dr. George Hall that this is in fact a retrogressive
slide. It is an unusual phenomenon but the Court is of the opinion
that Dr. Hall is correct in his analysis of the situation herein.

Further, the Court is of the opinion that respondent, once on
notice of the situation on U. S. Route 19, took immediate and
reasonable action to prevent any further drainage onto claimants'
property from the landslide and excess water flowing across the
road onto their property. The Court finds that the terrain in this
area of U. S. Route 19 is typical of many areas in West Virginia
which are subject to landslides. In the instant claim, claimants
have failed to established that respondent maintained U. S. Route
19, in Marion County, in a negligent manner. While the Court is
sympathetic to the situation of claimants, the fact remains that
there are many factors which have brought about this particular
landslide problem affecting their property, including the unusually
high water in 1985, the natural drainage area and the location of
the residence. Consequently, there is insufficient evidence of
negligence on the part of respondent upon which to base an award.

In accordance with the finding of facts and conclusions of law
stated herein above, the Court is of the opinion to and does deny
this claim.

Claim disallowed.
__________________