OPINION ISSUED JANUARY 23, 1998
KENHILL CONSTRUCTION COMPANY, INC.
VS.
WEST VIRGINIA REGIONAL JAIL AND FACILITY AUTHORITY
(CC-95-137)

Carl L. Fletcher, Jr. and Robert A. Lockhart, Attorneys at
Law, for claimant.

John S. Dalporto, Senior Assistant Attorney General, and
Jeffrey G. Blaydes, Assistant Attorney General, for respondent.
STEPTOE, JUDGE:

The claimant contractor, Kenhill Construction Company, Inc.,
brought this claim which arises out of the construction of the
Southern Regional Jail located in Raleigh County. Claimant
contractor (hereinafter referred to as Kenhill) entered into a
contract with respondent, West Virginia Regional Jail and Facility
Authority, on July 28, 1992, for the construction of the Southern
Regional Jail facility. Respondent gave its notice to proceed to
Kenhill on that same date, July 28, 1992. The terms of the
contract provided that Kenhill would have 600 days in which to
build the facility. The regional jail was actually completed on
July 14, 1994, 89 days beyond the planned contract completion date
of March 20, 1994. The failure to complete this construction
project within the 600 days provided by the terms of the contract
formed the basis of this claim by Kenhill as it alleges that the 89
days required for the completion of the project were the result of
unforeseen latent subsurface conditions. Kenhill alleges damages
in the amount of $774,734.00. Included in this total is the amount
of $177,134.00 for liquidated damages assessed by respondent and
interest upon the liquidated damages of $38,255.00.

Kenhill alleges that the unforeseen latent subsurface
conditions caused it to incur indirect costs including costs
related to inefficiencies in its construction of the project, costs
for its acceleration efforts in an attempt to complete the project
in a timely manner, additional expenses for backfill material,
dewatering, equipment, management personnel, travel expenses,
employee benefits, and costs for fuel and lubricants for equipment,
utilities, escalation of Workers' Compensation Premiums for labor,
and home office overhead and loss of profit. Kenhill also urges
that the liquidated damages wrongfully assessed by respondent and
the interest thereon be made a part of the damages awarded to it.

Respondent contends that Kenhill failed to provide timely
notice in accordance with the terms of the contract as to its
intention to make a claim for indirect costs related to the delay in the completion of the project. For this reason, respondent
contends that the claim fails in its entirety and should be denied
by the Court. Furthermore, respondent contends that actions on the
part of Kenhill and its subcontractors were the cause for the delay
in completing this project as well as certain weather factors, and
it was not the unforeseen latent subsurface conditions that caused
any delay.

It is necessary for the Court to begin its discussion of the
this claim by describing the construction of the Southern Regional
Jail as adduced from witnesses during the nine days of hearing this
claim which took place February 1997 and May 1997. The Court then
will address each of the issues raised by the parties in the
context of the evidence, and lastly, the Court will address the
issue of damages.
FINDINGS OF FACT
CONSTRUCTION OF THE SOUTHERN REGIONAL JAIL

As stated hereinabove, Kenhill entered into a contract (known
as a Purchase Order) with respondent for the construction of the
Southern Regional Jail with notice to proceed being given Kenhill
on July 28, 1992. Kenhill's contract provided that it would be the
general construction trades contractor meaning that it would have
the responsibility for coordinating the activities of all of the
prime contractors on the project. The architect for this project,
having been contracted for the job by respondent, was ZMM/CRA
(hereinafter referred to as ZMM) and it commenced the project by
holding a pre-construction conference on August 18, 1992. The
schedule provided at that meeting by Kenhill indicated that it
intended to pour slabs on grade between October 14, 1992, and
December 16, 1992. Pouring the slabs on grade was determined to be
the first construction step necessary by Kenhill as the project as
constituted, consisted of several pods for a block building
requiring thousands of concrete masonry units. Excavation to a
depth of 15 feet below subgrade or to rock was to begin that week
when Kenhill immediately encountered a large amount of subsurface
water. The plans prepared by ZMM for this project indicated that
a large French drain was beneath the surface of the ground on which
the regional jail was to be constructed, said drain having been
placed there previously during the construction of I-64 which abuts
upon this project on the project's southerly side. Although
Kenhill attempted to locate this French drain, it was to no avail.
On September 18, 1992, respondent determined that Kenhill would
have to install a large French drain with a connecting finger drain
and a small curtain drain. This work was defined in a change order
entered into by the parties and designated as GT-01.
Although the
normal designation would be CO-01, Kenhill as the general
contractor had all of its change orders designated by letters GT
meaning general trades contractor. Kenhill proceeded to excavate
below the planned excavation grade to place the French drain. The
French drain extended from the area southeast of E pod (the in-take
area) through the area of D pod to the northwest corner of A pod (the out-flow area). The trench was approximately seven to eight
feet in depth and six feet in width with a rubber membrane placed
in the bottom and on the sides, large rocks layered on the bottom,
then a layer of gravel, and finally covered with a layer of filter
fabric. This structure allowed for drainage from the interstate
through the construction site to a marsh located adjacent to the
site on the west side. The French drain and the curtain drains
were deemed by the parties to be necessary to protect the
engineered fill from subsurface water and, in turn, to protect the
integrity of the slabs on grade which would form the pad for the
jail facility. Kenhill and respondent agreed upon the terms of
payment for the direct costs of this extra work and Kenhill was
paid accordingly. These directs costs are not in issue in this
claim.

However, the construction of this French drain altered the
sequence planned for the construction of the various pods for the
jail facility. These pods were designated as A pod, B pod, C pod,
D pod, and E pod. A pod, B pod, and C pod were the areas of the
jail for housing prisoners while D pod and E pod were visitor and
administration areas. A pod was a maximum security area and had
different security requirements than B pod and C pod. Originally,
Kenhill planned to construct the pods beginning with E pod, then C,
D, B, and A pods, but it started excavating at E and D pods in it
efforts to find the French drain, then went to B and C pods when it
was determined that either the French drain was not there or that
Kenhill just could not find it.
Whether the drain noted on the
plans by the architect exists has never been determined. In any
event, the unplanned construction of the French drain by Kenhill
began on or about September 18, 1992, the final decision having
been made by respondent and its architect as to the remedial
measures to be taken for the extensive water problems at the site.
The French drain ran east to west through the project with a
curtain drain around the south end of B pod. This work was
completed on November 13, 1992.

During the months of September through December, Kenhill was
excavating at various areas and placing the engineered fill in
lifts as required by the terms of the contract. Footers for the
building were also being laid. On January 12, 1993, Kenhill was
directed by respondent to halt all work in the area of B pod while
a decision was made as to the course of action to be taken at this
site due to continuing subsurface water problems. Kenhill
installed a second curtain drain around the south end of B pod when
it became apparent to respondent that the subsurface water problems
were continuing to hamper construction in this area. This work was
later confirmed and paid for by GT-02. The second curtain drain
alleviated the water problem, but another problem was encountered
which concerned respondent. The integrity of the engineered fill
at B pod was believed to have been affected by subsurface water
problems. At a meeting of the parties in Charleston on April
21,1993, a decision was made to attempt a pressure grouting procedure to stabilize the soil beneath B pod. This course of
action was thought to be a way to avoid removing all of the
engineered fill which had already been placed. Respondent, through
its architect and engineer
Respondent's engineering firm for
this project was Triad Engineering, Inc., directed that EB
Consultants, Inc., should be used for the work, but after several
weeks of unsuccessful efforts to engage this company as the
subcontractor, Kenhill entered into a subcontract with Intrusion
Pre-Pakt. This took several additional weeks. Thus the work on B
pod was not completed until June 23, 1993. The original change
order for this work, GT-03, was for a guaranteed maximum price of
$85,000.00, but Kenhill was paid its actual costs which were
approximately $51,000.00. These direct costs are not in dispute.

The weather during the 1992-93 winter months was another
obstacle to Kenhill in its progression of the project. There was
wet weather in February and a severe snow storm in March 1993
resulted in a shut-down of the project for two weeks. Kenhill
continued to pour footers for the pods as weather permitted, but no
slabs on grade were poured at the site until April 18, 1993. The
last slab on grade was poured on July 20, 1993, at the site for A
pod, approximately seven months after the originally planned date
of December 16, 1992, for the completion of the slabs on grade.

During the construction season of 1993, Kenhill's masonry
subcontractor manned the project such that the block structures for
C pod, D pod, E pod, and B pod were under roof by the fall.
However, A pod was not roofed until late 1993 and was not "dried
in" until the spring of 1994. The area of A pod had been used for
storage of material during excavation activities so the engineered
fill was placed there last and it did not dry for some months due
to having been subjected to winter weather during the 1992-93
season. The fact that A pod was not "dried in" until the spring
1994 became a critical issue to Kenhill for the completion of the
project.

During the 1994 spring, Kenhill had a subcontractor engaged in
painting the pods and it was engaged itself in performing the final
work on the project. During this same period of time there was
work being completed by the other prime contractors. There were
punch list items to be accomplished and this process took several
months. The majority of the punch list work was the responsibility
of Kenhill's painting subcontractor, NLP Enterprises (hereinafter
referred to as NLP). The completion date provided in the contract
was March 20, 1994, but Kenhill did not receive a certificate for
substantial completion from ZMM until June 17, 1994.

Thus, the Southern Regional Jail was ready for occupancy.
Kenhill continued to assert its claim as first stated in its
December 20, 1993, letter based upon events which had occurred
during construction. Respondent assessed liquidated damages
against Kenhill for the 89 day delay in the completion of the
project and an additional amount of retainage for warranty issues.

The Court, having stated the basic relevant facts adduced
during the hearing of this claim, now proceeds to the consideration
of the various issues presented to it during the hearing. These
issues will be considered individually.
ISSUE OF NOTICE
The respondent herein has put forth with some particularity its
position that Kenhill failed to give it notice in a timely manner
of its intentions to make a claim for indirect costs resulting from
the delay in the completion of the Southern Regional Jail as
required by the terms of the contract. Respondent relies upon
language in its contract with Kenhill as well as language on the
change orders, particularly GT-01, GT-02, GT-03 and GT-04. The
General Conditions to the contract provide as follows:
§4.3.8.1 If the Contractor wishes to make Claim for an increase in
the Contract Time, written notice shall be given. The Contractor's
Claim shall include an estimate of cost and of probable effect of
delay on progress of the Work. In the case of a continuing delay
only one Claim is necessary. (Emphasis supplied.)


§4.3.3 Time Limits on Claims. Claims by either party must be made
within 21 days after occurrence of the event giving rise to such
Claim or within 21 days after the claimant first recognizes the
condition giving rise to the Claim, whichever is later. Claims
must be made by written notice. An additional Claim made after the
initial Claim has been implemented by Change order will not be
considered unless submitted in a timely manner. (Emphasis
supplied.)
It is uncontroverted that the claim by Kenhill for indirect costs
based upon delay was put forth with particularity in correspondence
from Kenhill dated December 20, 1993. Kenhill takes the position
that the notice was timely because this was the time at which it
became fully cognizant that it could not complete the contract by
March 20, 1994, due to its inability to complete A pod.
Respondent is of the opinion that the language on the face of the
change orders provides the contractor with the opportunity to give
notice of its claim for additional time needed to complete the
project as it contains the following statement:
"The Contract Time will be (increased) (decreased) (unchanged) by
( ) days."
This space was left blank by Kenhill as was the next line on the
GT-01 change order which states:
"The date of Substantial Completion as of the date of this Change
Order therefore is"
GT-01 was executed by Kenhill on January 25, 1993, although the
work was completed in November 1992. This was the work for the
French drain and certain finger drains necessitated by the
unforeseen latent subsurface conditions. Kenhill contends that at that point during construction of the project it did not have
reason to believe that additional time would be needed to complete
its work; therefore, it could not have completed these blanks with
any degree of certainty. Likewise, the change orders for the
additional curtain drain at B pod (GT-02) and the pressure grouting
work (GT-03) had the same spaces blank. These were executed by
Kenhill on May 19, 1993, and June 1, 1993, respectively. On
September 29, 1993, GT-04 was executed by Kenhill with language
that
"The date of Substantial Completion as of the date of this Change
Order therefore is March 20, 1994."
On GT-05 executed on November 11, 1993, the line for days had "(0)
days." and the date of substantial completion as March 20,1994.
GT-06 executed on February 11, 1994, (executed by the parties after
Kenhill had made its claim known to respondent by letter dated
December 20,1993) had a blank for days and the substantial
completion date of March 20, 1994. The Court makes specific
reference to the language of the change orders as respondent relies
heavily on this language in its theory of a lack of notice by
Kenhill of its claim for delay. However, respondent was certainly
aware of the unforeseen latent subsurface condition as it worked
with Kenhill to determine any remedial work necessitated by the
water on the project, and it directed the remedial work made
necessary by these water problems. There were specific references
to time impact in letters dated April 22, 1993, and May 11, 1993,
that accompanied both GT-01 and GT-02, respectively, wherein
Kenhill stated

"Any schedule or time impact is not included and has yet to be

determined."
Kenhill's testimony as well as that proffered by the respondent
established that at the time the French drain, curtain drains, and
pressure grouting work was on-going, Kenhill believed that it would
be able to complete the project on or before March 20, 1994. It
intended to make up any delay in pouring the slabs on grade,
originally scheduled for completion in December 1992, by executing
the block work portion of the work in an accelerated and expedited
manner; in fact, this was almost accomplished by Kenhill. It is
also obvious that the language in the change orders could not have
been so crucial to the parties as GT-07 did not have any language
change as to the contract time (marked [0] days and completion date
of March 20, 1994) when both parties were well aware of Kenhill's
claim for additional time to complete this project by that date.
CONCLUSIONS OF LAW AS TO THE ISSUE OF NOTICE

The Court is aware that the issue of notice is one of the most
important issues in this claim and it will be addressed prior to
the consideration of any other facet of the claim. Respondent's
position that the whole claim fails due to the lack of timely notice by Kenhill rests with its interpretation of certain claims
decided by this Court previously. In the claims of Holloway v.
Div. of Highways, Unpublished opinion (1991), Westbrook
Construction, Inc. v. Div. of Highways, (Unpublished opinion), and
Tri-State Asphalt, Inc. v. Div. of Highways, (Unpublished opinion),
the Court considered claims for damages due to extra work not
contemplated by the terms of the contract and held that written
notice to the owner must be provided in order that the owner and
the contractor both have an opportunity to accurately document the
work being performed by the contractor so there could be a
comparison of the costs incurred. The work performed by Kenhill
per the change orders for the French drain and the curtain drains
constituted the extra work on this project; however, both parties
kept records for the labor and equipment so that the cost of the
extra work was documented and paid for by the change orders.

The damages claimed by Kenhill in the instant claim are
indirect in nature as these flow from the extra work resulting from
the discovery by the parties that there were unforeseen latent
subsurface conditions. Work done in the winter which was
contemplated by the contractor to be done in more seasonable
weather, for instance, may result in inefficiencies on the project.
Thus, a claim based upon a changed condition such as unforeseen
latent subsurface conditions constitutes a breach of contract by
the owner and the same principle of notice does not apply. C.J.
Langenfelder, Inc. v. Dept. of Highways, 8 Ct.Cl. 193 (1971).
Notice is not the crucial issue in a claim of unforeseen latent
subsurface conditions as it is in extra work claims. The work
being performed is contemplated by the contract and both parties
can be expected to maintain all the necessary records to document
the direct costs being charged against the contract. However, there
may be accelerated activity by the contractor, inefficiencies in
performing its work, or a change in the sequence of the work
causing additional costs in performing the same work. These are
indirect costs not contemplated by the parties. The delay in the
progress of the work is not known by either party until the work
progresses to a point that the completion of the contract is not
possible within the contract time. There certainly was notice to
respondent of the changed physical condition on this project as
respondent had to determine the remedy to correct the changed
physical condition not contemplated by the parties. Once the delay
appears to be a reality then, and only then, the terms of the
contract requiring notice to the owner become a matter of
importance. The Court has determined that the state of mind of the
parties during the 1992-93 winter was that the project would be
completed timely; therefore, the issue of notice does not bar
Kenhill's claim based upon delay as put forth in its letter of
December 20, 1993.
DELAYS ON THE PROJECT

As part of the delay issue, the Court first must address the
matter of the schedules provided to respondent throughout the construction of this facility. Emphasis was placed upon the
so-called Strickland schedule (a computer generated program known
as Primavera) of January 22, 1993, such that the Court must comment
upon this aspect of the claim. The schedule was prepared by John
Strickland, Project Manager on this project and a Vice President of
Kenhill. This was the only schedule to show an early completion
date of December 1993. The schedule was based upon a January 7,
1993, data date at which time the major problems with the shut down
of B pod had not yet occurred. Also, John Strickland left the
project before this event occurred. All of the other schedules
showed a completion date of March 20, 1994, per the contract time.
The personnel most closely in contact with the project, being
Michael Leach for Kenhill and Henry Breeden for respondent, agreed
that the monthly "look ahead" schedules actually used on the
project provided all of the contractors on the job with the true
picture of what could be anticipated to be accomplished monthly.
This may not meet the specific terms of the contract, but with the
problems resulting from the water issue, this scheduling method was
considered appropriate at the time to meet the needs of the
contractors. The bar charts put forth by Kenhill did provide a
more accurate schedule for "as planned" activities. Respondent's
expert used the Strickland schedule to form his basis of the
"remaining days analysis" theoretically to prove that Kenhill
should have completed the project by March 20, 1994, per the 600
days in the contract. Since the Court does not give much weight to
the Strickland schedule, the expert's analysis does not provide the
Court with substantial and conclusive evidence that Kenhill should
have completed the project on time and is, therefore, solely
responsible for the 89 days of delay in the completion of the
project.

The issue of the completion of the slabs on grade forms
Kenhill's basis for the delay of the completion of this project.
Kenhill desired to pour all of the slabs on grade by mid-December
1992 in order to have a platform on which to proceed with the
masonry work. The regional jail is a block project by nature so
the sooner block can be laid, the sooner the project can progress
to completion. The slabs on grade were scheduled for the front 20
per cent of the project time, but actually took 60 per cent of the
total contract time. As soon as Kenhill came on the project, its
schedule was disrupted by the unforeseen latent subsurface
condition, i.e., the water problems. Kenhill could not proceed
until the water problem was addressed by respondent's design
engineer and architect. Of course, Kenhill was able to man the
project to perform some tasks which had to be done, but excavation
activities were limited until the decision to excavate the large
French drain and the curtain drains was made by respondent and the
drains were in place. Then Kenhill had problems with where to put
wet material excavated. Its sequence for the areas to be completed
with the engineered fill was disrupted. Its attempt to recover the
lost project time for the unforeseen latent subsurface condition was evident in the way the masonry work progressed during the
summer of 1993. In fact, Kenhill was able to recover a substantial
amount of the lost time. Its inability to complete A pod and have
it "dried in" by the winter of 1993 affected the completion of the
project. The Court is of the opinion that the late completion of
A pod was a direct result of the water problems experienced early
in the project when the slabs on grade could not be poured per the
original plan. This finding by the Court leads to the conclusion
that the delay in the completion of the project was caused by the
unforeseen latent subsurface conditions. Therefore, the Court
attributes the delay to circumstances beyond the control of
Kenhill.
MASONRY SUBCONTRACTOR ISSUE

The masonry subcontractor for Kenhill was Bat Masonry.
Personnel from this company came onto the project on November 23,
1992, which was nine days after masonry work could have actually
begun. In accordance with the terms of the contract, Bat Masonry
was required to submit a cold weather plan to respondent for
approval as well as other submittals. Respondent contends that
part of the 89 day delay is attributable to the failure of Bat
Masonry to start its work timely and to submit its cold weather
plan and other submittals when it came onto the project. At this
early stage of construction in November 1992, the footers were
being placed and Bat Masonry's employees were stockpiling block at
various locations in preparation to begin its work. It later had
to shut down its workforce on the project due to the shut down of
B pod in January 1993. The evidence establishes that Bat Masonry
had employees on-site and working prior to the approval of its cold
weather plan and other submittals. The Court does not believe that
any time was lost on the project due to failure to act on the part
of Bat Masonry. In fact, documentation submitted to the Court
substantiates Kenhill's assertion that its masonry subcontractor
manned this project in an exemplary manner in an attempt to bring
the project to completion in March 1994. The Court has determined
that Bat Masonry did not cause any delay as contended by
respondent.
DELAY BASED UPON WEATHER

There were delays on this project occasioned by events other
than the delay in pouring the slabs on grade. Weather was a factor
on the progression of this project during the winter of 1992-93.
The testimony and evidence established that Kenhill was forced to
shut down the job for a severe winter snowstorm during March 1-18,
1993. In its December 20, 1993, letter to respondent putting forth
its claim, Kenhill lists delay occasioned by weather at 36 days due
to abnormal amounts of precipitation during February and March
1993. The testimony for both parties acknowledges that weather
certainly did affect the progress of work during this time frame.
However, the schedule for performance of the contract prepared by Kenhill included a certain number of days for "float" for the
completion of various critical path items. For a contractor to
ignore the severe winters known to be the norm for the Beckley area
is then the contractor's error in judgment and not the fault of the
respondent. The General Conditions in the contract state as
follows:
§4.3.8.2 If adverse weather conditions are the basis for a Claim
for additional time, such Claim shall be documented by data
substantiating that weather conditions were abnormal for the period
of time and could not have been reasonably anticipated, and that
weather conditions had an adverse effect on the scheduled
construction.
The Court does not believe that 36 days of the delay alleged for
weather is fair and reasonable and, further, it is unsubstantiated
by the record. The Court has determined that a portion of the
delay in the completion of the project is attributable to weather
factors.
PUNCH LIST DELAYS

There was testimony during the hearing concerning the punch
list process and the events that occurred during the period from
March 1994 through the completion of the project in June 1994.
Kenhill takes the position that the process took far longer than
necessary by reason of events related to other prime contractors.
Respondent on the other hand contends that the delay in the punch
list process was the fault of NLP, the painting subcontractor to
Kenhill, and that Kenhill is not entitled to any delay for this
period of time. The alleged paint problems were based upon the
fact that respondent was demanding a certain level of perfection
which was not met by NLP, such that eventually there was a
determination made as to which level of anticipated paint finish
would be required in the various pods. This appeared to resolve
the problems and NLP completed its work. The evidence in this
claim supports the contention of the respondent that NLP was not
performing its subcontract as anticipated and that even Kenhill
appeared to be frustrated by the progress and performance of its
subcontractor. The Court is of the opinion that NLP did not
perform as normally anticipated by an owner such as respondent, and
failed to complete the painting of the jail in a timely and
workmanlike manner.

Other on-going problems during the punch list process are
attributable to other aspects of the project. There were problems
with the day room tables placed in each of the pods providing
living quarters for inmates. These specially ordered tables were
being furnished by Peterson Enterprises, a subcontractor of the
prime contractor Norment Industries, W.S.A. Inc., which had its own
contract with respondent. The first problem was with the gussets
attaching the tables to the floor and the second problem was with
the inadequacy of the seats at the tables. The table gussets were
to be secured to the floor in each pod, but there was a problem with the gussets being too loose. After the correction of this
problem, the floors had to be finished by NLP. NLP also had to
paint the tables as well as the seats. There was a problem with
the welds for the seats and the correction entailed the
installation of a second seat cover being fitted over the original
seat. Peterson finally completed the corrections to the seats on
June 22, 1994. These were problems solely in the control of the
respondent.

There was also a problem with Security Fence Company in its
installation of the fence and gates at the jail. Kenhill could not
finish its final seeding and mulching of the grounds surrounding
the facility until such time as the fencing was in place. The
fence contractor was under the control of respondent, and the fence
was not in place until May 20, 1994.

On April 25, 1994, the Fire Marshal inspected the project for
a Certificate of Occupancy which was not granted because there were
items listed to be accomplished before such Certificate could be
given. The items listed were minor on the part of Kenhill, but
other items listed were under the control of the respondent. The
Court considers all of these items to be accomplished during the
punch list process to be de minimis in time as other major issues
were on-going at the time. The Court concludes that was no delay
in the completion of the project based upon the fact that the Fire
Marshal's Certificate of Occupancy was not granted for the project
until June 20, 1994.
Similarly, the Court does not give any merit to respondent's
contention that Kenhill's steel erector, Summit Erectors, was off
the job for two to three weeks in 1994. There was no general work
stoppage for this period of time and Kenhill continued with the
masonry work on the pods during this time frame. Respondent could
have shut down the project had this been such an important event.
ISSUE OF DELAYS - FINDING OF FACT BY THE COURT

The Court finds that the number of days delay attributable to
the owner and the number of days attributable to adverse weather as
determined by the Court, grossly exceeds the number of days by
which Kenhill failed to meet the original contract completion date
notwithstanding any delays attributable to the performance of NLP.
DAMAGES

Kenhill put forth a theory on inefficiencies which is one of
first impression for the Court. Kenhill asserts that its
inefficiencies can be quantified by using a percentage method
developed by the U.S. Army in a study of airport runway
construction and repairs. The inefficiencies allegedly occurred
when Kenhill had to perform construction work in winter weather,
specifically during the period from December 1992 through April
1993, which would have been performed during the fall months of
1992 but for the unforeseen subsurface conditions encountered at
the beginning of the project. The formula presents a method for a daily calculation of the windchill factor based upon temperature
and wind. Then a composite effective rate for the period is
calculated. The percent calculated for the winter of 1992-93 by
Kenhill was 28.3%. This percentage was multiplied by labor costs
with a resulting loss calculated at $24,433.00; for equipment the
loss was calculated to be $11,193.00. Kenhill used four months in
its calculation of inefficiencies for equipment, but only three
months for labor. This seems inconsistent to the Court; therefore,
only the months of December 1992 through March 1993 will be
considered under any theory of inefficiency due to weather. As to
the U.S. Army theory, it seems logical to the Court that a
contractor will incur inefficiencies for both its equipment and
labor during winter months. However, to attempt to calculate an
exact percentage may stretch that logic somewhat. The Court is of
the opinion that Kenhill was not performing sufficient work during
the months of January through March 1993 to assess any coefficient
for alleged inefficiencies. The record establishes that the weather
prevented any appreciable amount of work from being performed.
Since it is not an item that may be ascertained with any degree of
accuracy, the Court has determined that it will not grant any award
based upon inefficiencies alleged by Kenhill. Thus the labor costs
in the amount of $24,430.00 and the equipment costs in the amount
of $11,193.00 are denied as these costs were calculated solely as
the costs of inefficiencies on the project.
ADDITIONAL EXPENSES

In prior claims based upon a changed condition, this Court has
determined awards on the theory of quantum meruit. Most of the
damages which issue from a changed condition are indirect costs to
the contractor. The reason for this is that work performed
pursuant to a change order is paid based upon quantified costs
agreed to by the parties. Indirect costs include those costs based
upon acceleration costs incurred in an attempt to make up time lost
due to delays on the project and additional costs incurred during
the extended time on the project. The Court analyzed the damages
put forth by Kenhill from the position of each party.

Additional expenses alleged to have been incurred by Kenhill
during the winter months include the items of backfill in the
amount of $22,113.00, unsuitable backfill material expenses in the
amount of $4,312.00, and dewatering expenses in the amount of
$9,116.00.

The unsuitable backfill material item represents the
excavation of wet material that had been placed by Kenhill as
engineered fill, but was rendered unsuitable due to the wet winter
conditions to which it was subjected when slabs on grade were not
poured when anticipated. The backfill material put in its place
was gravel purchased by Kenhill. The contract provided for
payment of the engineered fill. Kenhill asserts this work was done
to accelerate the project. These items are considered by the Court
to be costs directly related to expenses resulting from the delay
on the project and the Court will include $26,425.00 in its award.

As to the dewatering item, Kenhill claims this amount for
extra dewatering of the footers due to the winter months and the
excess water on the project. There was an item in the contract for
dewatering as this was anticipated due to weather conditions, but
Kenhill asserts that the item exceeded expectations due to the
particular conditions on this job. The Court has determined that
Kenhill experienced excessive water on this project which cannot be
attributed just to the weather. Therefore, the Court will consider
this item in the amount of $9,116.00 as part of the damages.

In addition to the items mentioned specifically above, Kenhill
submitted an extensive list of its damages for the period of March
20, 1994, through project completion on July 14, 1994. Certain of
these items have been considered by the Court to be actual costs
incurred by Kenhill during the March through June 1994 time frame.
Other items are considered by the Court to be speculative in nature
or in previous contract claims which have been denied by the Court.
Therefore, the Court will not consider the home office overhead
item, even though Kenhill used the Eichleay Formula to calculate
this amount. The Court considers this element of damages to be
speculative in nature and it has consistently refused to speculate
as to home office overhead in contract claims. The Court also
denies wage escalation costs, Workers' Compensation escalation
costs, and the vehicle expense item for the superintendent. The
contract provides for profit at 15% which has been calculated by
the Court upon its award for those items stated hereinabove.
LIQUIDATED DAMAGES
At the close of this project, respondent assessed liquidated
damages against Kenhill alleging that the 89 days delay in the
completion of this project was attributable to actions on its part
during construction. Liquidated damages in the amount of
$89,000.00 calculated at $1,000.00 per day in accordance with the
terms of the contract were withheld from Kenhill at the completion
of the project. An additional amount of $88,134.00 was withheld
for retainage for alleged warranty problems existing on the project
at this time which were not addressed in any detail by respondent.
Kenhill asserts that it is entitled to recover $177,134.00, plus
interest. The Court, having addressed the issue of the delay in
the completion of the project, is of the opinion that Kenhill is
entitled to recover the assessed liquidated damages. The
completion of the regional jail beyond the date of March 20, 1994,
was the result of many factors some of which involved the other
prime contractors. Therefore, the Court will grant Kenhill the
amount of $177,134.00 plus interest as provided by the terms in the
contract.
In accordance with the findings of fact and conclusions of law as
stated hereinabove, the Court grants an award as an equitable
adjustment to Kenhill for the unforeseen latent subsurface
conditions encountered in its construction of the Southern Regional
Jail and for liquidated damages, in the total amount of $380,862.25. Additionally, interest upon this award has been
calculated in accordance with §13.6.1 of the contract at the legal
rate from the 17th day of August, 1994, through and including the
date on which this opinion is issued.

Award of $489,519.39.