










OPINION ISSUED APRIL 2, 2002
CC-00-160
IN THE COURT OF CLAIMS OF THE STATE OF WEST VIRGINIA
HOURLY COMPUTER SERVICES
VS.
DEPARTMENT OF HEALTH AND HUMAN RESOURCES
(CC-00-191)

Larry G. Kopelman, Attorney at Law, for claimant.

Joy M. Bolling, Assistant Attorney General, for respondent.
GRITT, JUDGE:

Claimant, a computer vendor, brought this action to recover
finance charges which it incurred during the completion of a
contract entered into with respondent for computers, software, and
installation of the computers. The finance charges, referred to as
interest by claimant, are in the amount of $13,476.67, which
represents the amount of this claim. The Court is of the opinion
to deny this claim for the reasons set forth herein below.
Further, respondent's motion to amend the style of the pleadings to
substitute the State Auditor in the place of the named respondent
is denied for the reason stated herein below.

On October 14, 1999, claimant and respondent entered into a
contract for the purchase of 600 computers, including software and
installation of the computers, for a purchase price of
$739,750.00. The contract (designated as Purchase Order DHS 31227)
provided for the completion of the contract within sixty ( 60) days
with a completion date of December 15, 1999. The first set of 200
computers was delivered and installed in November 1999 After the
hearing of this claim, claimant provided copies of Service Orders
and an invoice dated November 29, 1999, in the amount of
$244,200.00 to support testimony that the respondent had received
an invoice for the first 200 computers, software, and installation.
This invoice was not paid by respondent. with the second set of 200
computers being delivered in early December 1999 and the last set
of 200 computers being delivered in late December 1999 or early
January 2000. An invoice in the original amount of $739,750.00 that serves as the basis for claimant's claim herein was dated
December 31, 1999, received by respondent on January 4, 2000,
signed by respondent's representative as certification of the
merchandise having been received on January 16, 2000, and paid by
respondent on or about March 10, 2000, in the final agreed upon
amount of $697,150.00. The amounts of $24,600.00 and $18,000.00
were deleted from the total of the original invoice for the reasons
discussed below. During this time frame, a dispute arose between
the parties as to the software required under the contract and the
delivery schedule for the computers. The parties ultimately agreed
to extend the installation of the software beyond the sixty (60)
days provided for in the contract. The Court has not been provided
the date the extension was granted. The parties also disagreed
concerning the license for the software. Claimant originally began
providing a software license with each computer, but respondent's
representative requested one license for all the computers
purchased by respondent. The respondent's insistence on one
license for all the software to be installed pursuant to the
contract occurred after the delivery of first 400 of the
computers, but claimant later agreed to provide the one license to
end this dispute. The final area of dispute was over the price of
the installation of the computers. Claimant delivered the last 200
computers, but many of these units were set up and installed by
respondent's personnel. A reduction of $5,000.00 in the charge for
the installation of the last installment of 200 computers was
eventually agreed to by claimant due to the reduced number of units
actually installed by claimant's personnel. However, a formal
vendor's complaint was filed with the Department of
Administration's Purchasing Division by respondent involving all of
the issues mentioned above which was resolved by the parties
through mediation.The documentation for the formal vendor's
complaint was provided to the Court after the hearing by counsel
for the respondent. This information was reviewed by the Court.
The first date which indicates a dispute between claimant and
respondent is that on an electronic message dated January 13, 2000.
A meeting was held on February 8, 2000, to discuss several issues.
While a formal vendor's complaint was made by the respondent, the
only date evident regarding the filing of the complaint is March 7,
2000. The respondent's vendor's complaint was resolved with the
respondent agreeing to pay to the claimant the sum of
$697,150.00.The parties did not provide the Court with the date
their dispute was mediated and resolved. The claimant apparently
purchased the computers and software sold to the respondent by
using an existing line of credit previously obtained by the
claimant from a lender of its choice. Claimant alleges that it was
not paid for the computers in a timely manner by respondent
resulting in unnecessary finance charges to it, and that it is
entitled to reimbursement of the finance charges.
The parties have raised issues regarding (1) the payment of
interest based on the provisions of a contract that is before the Court for interpretation, (2) the payment of pre-award and
post-award interest on awards made by the Court, (3) the inclusion
of finance charges incurred by a vendor as an element of its
overhead expense as an element of damages to be considered by the
Court in making an award, and (4) the applicability of WV Code
§5A-3-54, generally referred to as the "Prompt Pay Act of 1990" to
certain claims that may be brought before the Court. The Court
will address each of the issues presented separately.
Contract Interest
WV Code §14-2-12, which sets forth the general powers of the Court
of Claims, states specifically that ". . .in determining the amount
of a claim, interest shall not be allowed unless the claim is based
upon a contract which specifically provides for the payment of
interest." The Court notes that there was no provision in the
contract between the parties herein that interest be paid to
claimant and therefore the claimant cannot recover any interest as
a part of its claim that is traditionally described as "contract
interest." The specific statutory disallowance of traditional
contract interest contained in WV Code §14-2-12 differs from the
general rule in West Virginia found in WV Code §56-6-27 that
states that "the jury, in any action founded on contract, may allow
interest on the principal due, or any part thereof, and in all
cases they shall find the aggregate of principal and interest due
at the time of the trial" and that "judgment shall be entered for
such aggregate with interest from the date of the verdict." See,
The First National Bank of Bluefield v. Clark, 191 W.Va. 623, 447
S.E.2d 558 (1994); Erikson Construction Co. v. Morey, 923
F.Supp.878 (1996); and Board of Education of McDowell County v.
Zando, Martin & Milstead, 182 W.VA. 597, 390 S.E.2d 796 (1990).
Pre-award and Post-award Interest

The disallowance of all interest but for the payment of
interest specifically required by contract by the provisions of WV
Code §14-2-12 is, in essence, a bar to the recovery of pre-award
and post-award interest. The prohibition against paying pre-award
and post-award interest on awards made by the Court contained in WV
Code §14-2-12 also differs from the statutory requirements of WV
Code §56-5-31 which mandates that "damages shall bear interest from
the date of the right to bring the same shall have accrued, as
determined by the court"and "that every judgment or decree for the
payment of money entered by any court of this State shall bear
interest from the date thereof, whether it be so stated in the
judgment or decree or not" at a rate of "ten dollars upon one
hundred dollars per annum." See, The First National Bank of
Bluefield, supra; Erikson Construction Co., supra; and Board of
Education of McDowell County, supra.; and Adams v. Nissan Motor
Corp. in U.S.A., 182 W.Va. 234, 387 S.E.2d 288 (1989).
Traditionally, the denial of both pre-judgment and post-judgment
interest violates the requirements of WV Code §56-6-31. Rakes v.
Ferguson, 147 W.Va.660, 130 S.E.2d 102 (1963).
Interest as an Element of Overhead Expense

In its claim, the claimant is attempting to equate the finance
charges that it incurred which are an element of its overheard
expense, to the interest that may be paid to a vendor pursuant to
the provisions of the "Prompt Pay Act of 1990." The "Prompt Pay
Act" requires that for purchases of services or commodities the
State Auditor shall issue a State check "in payment thereof within
sixty days after a legitimate uncontested invoice is received by
any of such agencies receiving the services or commodities. Any
state check issued after sixty days shall include interest at the
current rate ...." Claimant alleges that this provision of the
"Prompt Pay Act" allows it to make a claim for interest in the
amount of $13,476.67, which said amount is actually the amount of
the finance charges incurred by the claimant in the satisfaction of
its contract with the respondent and not the amount of interest as
contemplated by the Act or calculated according to the provisions
of the Act.

It is a mistake in fact and law to equate the payment of
finance charges incurred by a vendor as an element of its overhead
expense while engaged in the general pursuit of a business
enterprise and the statutory interest that is required by the
provisions of the "Prompt Pay Act." The Court can find no
statutory authority or case law to support the claimant's
contention that it is entitled to recover the finance charges that
it incurred while doing business with the respondent. Without
statutory or case law authority to include finance charges incurred
as an element of overhead expense by a vendor doing business with
a State agency in a claim against the agency for breach of contract
as an element of the vendor's damages, the Court declines to chart
new territory in that regard.
Prompt Pay Act of 1990
The respondent contends that the "Prompt Pay Act " does not
apply to this claim for the reasons that no "legitimate
uncontested invoice" had been received by the respondent for
payment and, therefore, there is no basis for the allegation that
the invoice was not timely paid. The respondent also asserts the
position that this Court lacks subject matter jurisdiction in this
claim on the basis that claimant has a remedy in the regular courts
of this State if it is proceeding under the "Prompt Pay Act." The
respondent contends that an action such as mandamus may be brought
in the courts of the State against the respondent concerning the
interest that may be due the claimant pursuant to the "Prompt Pay
Act."

The issue of jurisdiction of a court with respect to any
action before it may be raised at any time during the proceedings,
even by the court itself. This Court is a court of limited
jurisdiction with only the subject matter jurisdiction being
specifically granted it by the Legislature in the creation of the
Court of Claims. WV Code §14-2-14(5) establishes this Court's
limited jurisdiction and provides that the jurisdiction of the
Court shall not extend to any claim ". . .with respect to which a proceeding may be maintained against the state, by or on behalf of
the claimant in the courts of the state."

In reviewing the language of the "Prompt Pay Act" the Court
notes certain deficiencies in the Act including, but not limited
to, the fact that there is (1) no mention in the statute for a
remedy if a vendor disagrees with the State Auditor in its
application of the interest provisions of the Act, (2) no time
frame or a method for resolving a disputed invoice, and (3) no time
limitation for making a claim for interest claimed to be due on
the part of a vendor.The provisions of WV Code§5A-3-54(d) states
that. . . the state agency initially receiving a legitimate
uncontested invoice shall process such invoice for payment within
ten days from its receipt: Provided, That in the case of the
department of health and human resources, the division of highways
and the public employees insurance agency, such invoices shall be
processed within fifteen days of their receipt. In spite of this
requirement, the respondent has not provided the Court with the
precise date the claimant's invoice was received and submitted for
payment. Because this Court is a court of limited jurisdiction and
even though the "Prompt Pay Act" as currently presented may be
deficient in many respects, the Court cannot conclude that it is
without subject matter jurisdiction to make an award of interest
that may be otherwise due a vendor pursuant to the Act.The State
Auditor is encouraged by the Court to develop, implement and
distribute to all State agencies and properly registered and
qualified vendors a uniform written policy regarding the
resolution of contested invoices submitted by vendors and when
interest may be due a vendor pursuant to the Act. The "policy"
supplied to the Court as Attachment B to the respondent's
Supplement to Previously Filed Motion To Dismiss is inadequate to
accomplish the purpose of the Act. The failure to develop and
implement such a policy frustrates the very purpose for which the
Act was adopted, that is, to encourage small West Virginia business
owners to do business with State agencies. To the extent that
this Court impliedly assumed jurisdiction to hear claims for
interest due a vendor pursuant to the provisions of the immediate
predecessor to the current "Prompt Pay Act" in R. L. Banks &
Associates, Inc. vs. Public Service Commission, 17 Ct.Cl. 159
(1988), said implication is hereby expressly denied.

The respondent also asserts that the claimant failed to pursue
its administrative remedy in its claim for interest under the
"Prompt Pay Act." The Court cannot consider the respondent's
argument inasmuch as the provisions of WV Code §5A-3-54 do not
contain an administrative process for reviewing a claim for
interest by a vendor and because no such procedural rules have been
promulgated by the State Auditor pursuant to the provisions of WV
Code §29A-1-1, et.seq., the State Administrative Procedures Act.

The Court is of the opinion to and does hereby deny the
respondent's motion to amend the style of the pleadings to
substitute the State Auditor in the place of the named respondent inasmuch as the claim presented by the claimant is a claim for
interest as an element of its overhead expense growing out of the
contract dispute with the respondent.

Therefore, for all of the reasons stated above, the Court is
of the opinion to and does hereby decline to recommend the payment
of this claim.

Claim disallowed.
CC-00-191
IN THE COURT OF CLAIMS OF THE STATE OF WEST VIRGINIA
CALLA SMITH AND HUBERT SMITH
VS.
DIVISION OF HIGHWAYS
(CC-00-369)

Claimants appeared pro se.

Andrew F. Tarr and Xueyan Zhang, Attorneys at Law, for
respondent.
PER CURIAM:

Claimants brought this action for damage to their property
which occurred when a large tree fell from respondent's right of
way onto claimant's building along County Route 1/11 in Wayne
County. The right of way at issue is owned and maintained by
respondent in Wayne County. The Court is of the opinion to deny
this claim for the reasons stated more fully below.

The incident giving rise to this claim occurred in the early
morning hours of September 6, 2000. Claimant Calla Smith resides
on the property where this incident occurred. She was asleep in
her bed when she heard a lot of loud noise coming from outside her
home. The property is located next to County Route 11/1, also
known as Bowman Hill Road, in Wayne County. Within a few moments,
a neighbor came to her door and told her that a large tree had
fallen on her building. The building served as both a barn and a
garage. One half of the building was two stories high and was used
as a barn and storage area for tools and other items while the
other half was used as a garage where Ms. Smith parked her pick-up
truck. The building was already built on the parcel of property
when Ms. Smith purchased it with the residence in 1968. However,
both Calla Smith and her brother Hubert Smith own the building. Claimants are not sure how long this particular building has been
on the property, but photos of the building taken in 1971depict a
structure that at the time appeared to be in sound condition.
Testimony adduced at the hearing also established that the building
was still in at least good condition just prior to this incident
and that it still had a solid foundation. The tree that fell on
the building was located on the respondent's right of way a few
feet from County Route 11/1, almost directly across the road from
claimants' building. The trunk of the tree was located
approximately 13.2 feet from the center line of the road and it was
growing from a small bank above a ditch line along the road. The
tree was a large White Oak with green leaves and many wide, long
branches. It was approximately thirty-eight inches in diameter.
Prior to this incident, the branches of the tree extended across
the road and hung almost completely over top of the claimants'
building which had been its condition for several years.

Ms. Smith testified that the tree crushed the left half of the
building that served as a barn. It destroyed the structure along
with most of the items stored in it, including small hand tools,
plows, wood, and extra tin. Fortunately, the tree did not land
directly on the garage section of the building, where Ms. Smith
parked her 1992 Ford truck. There was only a small scratch on the
truck from the fallen tree. Respondent was called to the scene to
remove the tree which was totally blocking the road and was lying
on top of what was remaining of the left side of the building.
Respondent's crew successfully removed the limbs off of the
building so as to not cause damage to the garage portion of the
building where Ms. Smith's truck was parked. Respondent hauled off
the debris and gave Ms. Smith the remaining quality wood to use as
firewood. The claimants left the garage portion of the building
standing throughout the remainder of the fall of 2000 and the
winter of 2001 so that Ms. Smith could park her truck in the garage
during this period. Claimants seek $27,000.00 in damages which was
the estimate provided to them by a contractor for the
reconstruction of a building comparable to the one destroyed by the
tree.

Claimants contend that respondent knew or should have known
that this tree posed a hazard for falling and that it should have
remedied this hazard prior to this incident by either cutting the
tree down or removing some of the larger limbs.

Respondent asserts that it did not have notice that this tree
posed a hazard and that it acted diligently in responding to this
incident.

Randolph Smith, Transportation Crew Chief for the respondent
in Wayne County at the time of this incident, testified that he is
responsible for responding to complaints regarding road conditions
or hazards. Mr. Smith is responsible for dispatching crews and the
proper material to the appropriate sites. He is familiar with
County Route 11/1 including the location where this incident
occurred. He testified that County Route 11/1 is a two-lane, blacktopped, secondary road. It is approximately twelve feet wide
in most places. Mr. Smith testified that the Right of Way Division
of respondent informed him that its right of way on County Route
11/1 is thirty feet. Mr. Smith was first notified of the incident
just prior to 7:00 a.m., when he received a telephone call. He
immediately dispatched a crew to the scene. Upon arrival, the crew
recognized that the situation was unique and problematic.
Therefore, they called Mr. Smith to the scene for his advice and
supervision. Mr. Smith testified that the tree was a large White
Oak and had fallen completely across the road and one half of
claimants' building. Mr. Smith and his crew determined that they
would remove the tree one limb at a time, instead of many at once,
so as to salvage the garage portion of the building. Respondent
was successful in doing so. According to Mr. Smith, the tree was
alive and had no signs of dead or decaying branches. All the
branches were strong and healthy with green leaves. In concluding
what caused this tree to fall, it was Mr. Smith's opinion that it
simply "uprooted." He stated that "the whole root bottom
upturned". However, Mr. Smith could not state what caused the tree
to do this. He testified that it was windy earlier that morning
when he came to work. There had not been any severe rain storms in
recent days and the area around the base and roots of the tree was
dry. According to Mr. Smith, there were no apparent reasons for
this tree to fall on that particular day.

The Court has held that respondent may be responsible for
dangerous trees or tree limbs on its property or rights of way.
The general rule adopted by the Court is that if a tree is dead and
poses an apparent risk, then respondent may be held liable. Wiles
v. Div. of Highways, 22 Ct. Cl. 170 (1999). However, when a
healthy tree falls and causes property damage as a result of a
storm, the Court has held that there is insufficient evidence of
negligence upon which to justify an award. Gerritsen v. Dept. of
Highways, 16 Ct. Cl. 85 (1986). Further, to hold respondent
liable, the claimant must establish by a preponderance of the
evidence that the respondent had actual or constructive notice of
the defect in question and a reasonable amount of time to take
corrective action. Chapman v. Dept. of Highways, 16 Ct. Cl. 103
(1986); Pritt v. Dept. of Highways, 16 Ct. Cl.8 (1985).

In the present claim, the Court is of the opinion that
claimant did not establish by a preponderance of the evidence that
respondent had notice that the tree at issue was at risk of
falling. Respondent had received no complaints about the tree. The
numerous photographs admitted into evidence establishes that the
tree was green and alive. Thus, respondent did not have actual
notice that the tree posed a risk of falling. The claimants could
not state with any degree of certainty what caused the tree to
fall, but only that the bottom foot or two of a small back portion
of the tree looked dead. One of claimants' witnesses was of the
opinion that the tree was rotted on its back side, but this side of
the tree was not visible from the road. The witness had no idea why the tree may have been partially rotted. No other logical
explanation for the tree to suddenly fall was provided by either of
the parties to this claim. This Court has consistently held that
an award cannot be based on mere speculation. Mooney v. Dept. of
Highways, 16 Ct. Cl. 84 (1986); Phares v. Div. of Highways, 21 Ct.
Cl. 92 (1996). For this Court to make a determination as to the
reason why the tree fell on the date of the incident herein would
require the Court to resort to speculation which it will not do.
Thus, the Court finds that respondent was not negligent in its
maintenance of County Route 11/1 or its right of way on the date
that the tree fell onto claimants' property.

In accordance with the findings above, the Court is of the
opinion to and does deny this claim.

Claim disallowed.

The Honorable Benjamin H. Webb, II, Judge, was not present at
the hearing of this claim, but he did take part in the decision
made by the Court and in the written opinion.
CC-00-369
IN THE COURT OF CLAIMS OF THE STATE OF WEST VIRGINIA
LARRY DAVID HOLDREN
VS.
STATE OF WEST VIRGINIA
(CC-00-461)

Lonnie C. Simmons, Attorney at Law, for claimant.

Barry L. Koerber, Assistant Attorney General, for respondent.
BAKER, JUDGE:

Claimant brought this action for an award pursuant to W.Va
Code §14-2-13a for being unjustly imprisoned for more than fifteen
years. The Court is of the opinion to make an award in this claim
for the reasons set forth below.

The facts giving rise to this claim began on December 28,
1982, when a woman jogging along Kanawha Boulevard in Charleston
was violently pushed over a hill and sexually assaulted by a man
approaching her from the opposite direction. The victim survived
this vicious attack, and on March 10, 1983, claimant Larry David
Holdren was arrested for the sexual assault based solely upon the
victim identifying his photograph from a photo array. When this
nightmare began in his life, he was 27 years of age. The photograph array shown to the victim also included a photograph of
claimant's identical twin brother. Claimant was indicted by a
Kanawha County Grand Jury on six counts of first degree sexual
assault on June 23, 1983, and was subsequently convicted of all six
counts on July 16, 1984. On February 21, 1985, claimant was
sentenced by Kanawha County Circuit Judge A. Andrew MacQueen to
serve ten to twenty years on each count with three of the sentences
to be served consecutively with the remaining three sentences.
Claimant was incarcerated in the State Penitentiary in Moundsville
on March 20, 1985, at which time he was 29 years of age. He was
imprisoned at that correctional facility until he was transferred
to Mount Olive Correctional Facility on March 20, 1995.

Claimant took every legal avenue available to him in an
attempt to gain his freedom while he was incarcerated. He
attempted to obtain physical evidence that may have been left by
the real assailant to prove that he was innocent of this terrible
crime. However, he was unable to obtain the physical evidence
necessary to conduct the scientific testing available at that time.
Claimant also exhausted all of his rights of appeal, as well as all
of his State habeas corpus rights and his federal habeas corpus
rights. Unfortunately, all of these efforts failed to provide any
legal relief, and claimant remained in prison for a crime he did
not commit. In 1997, upon the claimant's request, his attorney
secured an agreement with the Kanawha County Prosecuting Attorney's
office to allow certain physical evidence in this case to be
examined by DNA experts. In a report issued on January 25, 1999,
by the DNA experts, it was determined that the claimant was not the
individual who sexually assaulted the victim. A hearing was held
on June 9, 1999, at which the DNA experts who performed the DNA
testing testified as to the test results which proved that Larry
Holdren was innocent of this crime. The Kanawha County Prosecuting
Attorney's office had several national experts at this hearing to
listen to the testimony and to provide advice on the issues. The
next day, June 10, 1999, the Circuit Court of Kanawha County
entered an Order reversing claimant's conviction and allowed his
release from prison. By Order made and entered on January 4, 2000,
the State dismissed the indictment against the claimant. Thus, it
was established that the claimant did not commit the offense for
which he was imprisoned for over fifteen years. At the time
claimant was finally free of this nightmare in his life, he was 44
years of age.

Claimant brought this action in accordance with the provisions
of W.Va. Code § 14-2-13a (a), (b), (d), and (e). After reviewing
the documentation submitted by the claimant, the Court has
determined that he has met the requirements of these sections;
therefore, he has an absolute right to a recovery.

The only issue the Court must address is the amount of the
award to be granted to the claimant herein. Undoubtedly, claimant
suffered an economic loss while imprisoned for over fifteen years
of his life. He was 29 years of age at the time of his incarceration and he was 44 years of age when he was finally free
of the charges made against him. The testimony adduced at the
hearing established that, at the time claimant was arrested in
March 1983, he was working on his undergraduate degree expecting to
graduate with a four year Bachelor's Degree in December 1983. At
the hearing of this matter, claimant presented expert testimony
from Roger A. Griffith, an economist, who performed an analysis of
expected economic loss on behalf of the claimant. This analysis
was performed to demonstrate the range of the wages and benefits
claimant lost while imprisoned. Mr. Griffith's analysis concluded
that claimant's expected economic loss of wages and benefits ranges
from a low figure of $735,370.00 which is based upon the average
wages of a worker in Kanawha County, to a high figure of
$1,338,827.00 based upon the average wages of a male with a
Bachelor's Degree. Mr. Griffith explained during his testimony
that he used conservative figures for computing the loss of
earnings in this claim; however, these amounts are based upon gross
earnings.

The Court reviewed these figures and all other facets of
claimant's pecuniary damages which include the past loss of
earnings due to incarceration and the impairment of future earnings
directly related to the imprisonment of the claimant, as well as
the loss of reputation, the loss of liberty, emotional stress, pain
and suffering in determining the amount of claimant's award.
Furthermore, it must be stated that the majority of claimant's
imprisonment was spent at the State Penitentiary in Moundsville, a
State facility which had the reputation as being an horrific
prison.

The Court is aware that there was a settlement between the
claimant and a third party which the Court has taken into
consideration in determining the amount of the award to be granted
to the claimant. Thus, taking all of the elements of damages into
account and considering that any award must reflect what is fair
and reasonable to both the claimant and the State of West Virginia,
the Court has determined that claimant is entitled to an award of
$1,650,000.00.

In accordance with the findings of fact and conclusions of law
as stated herein above, the Court is of the opinion to and does
make an award to the claimant in the amount of $1,650,000.00.

Award of $1,650,000.00
CC-00-461
IN THE COURT OF CLAIMS OF THE STATE OF WEST VIRGINIA
JOHN MYERS
VS.
DIVISION OF HIGHWAYS
(CC-01-106)

Claimant appeared pro se.

Xueyan Zhang, Attorney at Law, for respondent.
PER CURIAM:

Claimant brought this action for damage to his 1993 Mitsubishi
G.T. which occurred when he was operating his vehicle on the
Interstate 77 northbound ramp, Exit 119, near Goldtown, Jackson
County, and the vehicle struck a metal plate in the road.
Respondent was responsible at all times herein for the maintenance
of Exit 119. The Court is of the opinion to deny this claim for
the reasons set forth below.

The incident giving rise to this claim occurred on December
29, 2000, at approximately 7:00 p.m. Claimant John Myers was
driving his vehicle down the ramp at Exit 119 off of I-77 at
Goldtown. The weather was clear and cold. The road surface was in
good condition. Mr. Myers was traveling between forty to fifty
miles per hour on the ramp, which he testified to as a long exit
ramp. Mr. Myers lives just a little over a mile from the Goldtown
Exit and he was on his way home. As his vehicle reached near the
half way point on the exit ramp, he felt a hard bump and heard a
loud noise as he drove over a patched area in the road surface. He
drove another fifty yards and turned left onto Route 21 when he
realized he had a flat tire. Mr. Myers took a flashlight and
examined the patched area to see what his vehicle had just struck.
He testified that he observed a metal plate that had sunk down
approximately two to three inches below the road surface. He
stated that when he stepped on this metal plate it would give a
little bit and he characterized it as spongy in nature. Mr. Myers
testified that he had driven this exit ramp for at least seven
years and had passed over this patched area hundreds of times
safely. He described the area at issue as a patched almost perfect
square like area. He also stated that it is adjacent to the white
edge line, but totally within the lane of travel. As a result of
this incident, claimant had to replace one wheel and tire and his
vehicle had to be aligned. Mr. Myers seeks an award of $591.43.
He did not have any insurance in force at the time of this incident
to cover these damages.

Claimant contends that respondent knew or should have known
that this metal plate and the manner in which it was covered
presented a potentially hazardous condition to the traveling
public.

Respondent asserts that it did not have notice of any hazard
at the location at issue until after this incident. Therefore,
respondent asserts it did not have a reasonable amount of time to
take corrective action.

Claimant explained that it was his belief that the last time
the exit ramp had been paved was in 1998 and that the contractor
who did so paved around the metal plate and left it exposed. He
stated that he assumed that respondent then came in and smoothed
out the area. Mr. Myers testified that the location at issue has
remained the same since approximately 1998 until the night at issue
when the metal plate apparently sunk down a few inches from the
pavement creating a large hole with a portion of protruding metal.

Bruce Leedy, the Regional Engineer for respondent, is
responsible for the area at issue. He testified that he was
contacted by the claimant after this incident occurred. Mr. Leedy
went to the scene in March 2001 to determine what the problem may
have been. He stated that it was obvious to him that a hole of
some sort had been patched recently and that this was probably the
second or third time that it had been patched. Mr. Leedy testified
that there had been some sort of patch there for at least two
years. However, Mr. Leedy could not testify as to the condition of
this location prior to March 2001.

Stanley W. King, supervisor for respondent at the Allen's Fork
Garage in Jackson County, oversees the maintenance of thirty-two
miles of Interstate 77 including the area at issue with which he is
familiar. Mr. King testified that an old drain had been covered
with a metal plate and patched with blacktop at the location where
claimant's incident occurred and it had been in that condition for
at least six years. He stated that when the old drain had stopped
working, respondent had covered it with the metal plate and then
blacktopped over the entire area. He was certain that there was
not any metal left exposed at all. Mr. King also stated that he
had not received any complaints regarding this location prior to
this incident. Further, he testified that on December 29, 2001,
respondent was on snow removal and ice control duty or "SRIC".
Respondent introduced into evidence a DOH-12 demonstrating that the
work crew was "cold patching" holes on I-77 and on Route 21. Mr.
King stated that respondent does not record the exact location of
every hole it patches during "SRIC", but he stated that if the
maintenance crew saw a metal plate exposed it would have repaired
it. He also stated that normal working hours for respondent at the
Allen's Fork Garage is from 7:30 a.m. to 4:00 p.m.

It is a well established principle of law that the State is
neither an insurer nor a guarantor of the safety of motorists on
its roads and highways. Adkins v. Simms, 46 S.E.2d 811
(W.Va.1947). To hold respondent liable, the claimant must
establish by a preponderance of the evidence that respondent had
actual or constructive notice of the road defect in question and a
reasonable amount of time to take corrective action. Chapman v. Dept. of Highways 16 Ct. Cl. 103 (1986); Pritt v. Dept. of
Highways, 16 Ct. Cl. 8 (1985). However, respondent owes a duty to
the traveling public to exercise reasonable care and diligence in
the maintenance of the highways of this State. Lewis v. Dept. of
Highways, Ct. Cl. 136 (1986).

In the present claim, the Court has determined that claimant
failed to produce sufficient evidence to establish that respondent
had prior notice that there was a hole or protruding metal at the
location of this incident. Although it is undisputed that
respondent was aware that there was a drain and metal plate covered
over by blacktop, respondent was not aware of any hazardous
condition at this location. The evidence established that
respondent was not informed of the problem until after the
claimant's incident. The Court is of the opinion that respondent
was not negligent in its maintenance of the I-77 Exit Ramp 119 at
the time of claimant's incident.

Accordingly, the Court is of the opinion to and does deny this
claim.

Claim disallowed.
CC-01-106
IN THE COURT OF CLAIMS OF THE STATE OF WEST VIRGINIA
HELEN O'DELL
VS.
DIVISION OF HIGHWAYS
(CC-01-119)

Michael R. Whitt, Attorney at Law, for claimant.

Andrew F. Tarr, Attorney at Law, for respondent.
PER CURIAM:

This claim was submitted to the Court for decision upon a
Stipulation entered into by claimant and respondent wherein certain
facts and circumstances of the claim were agreed to as follows:

1. Claimant's residence is located at 410 8th Street,
Rainelle, in Greenbrier County.

2. In August 2002, representatives of respondent and of the
Town of Rainelle met to discuss the drainage on Greenbrier Avenue,
which proceeds through the Town of Rainelle and is maintained by
respondent. At that time, the representative for the respondent was advised that a manhole on Greenbrier Avenue was part of
Rainelle's abandoned sanitary sewer system and was no longer in
use.

3. Based upon the information obtained from Rainelle's
representative, respondent proceeded to remove the manhole from the
roadway and fill the abandoned sewer line with concrete. This work
was completed in the fall of 2000.

4. Claimant's home was damaged by high water during the month
of January 2001. Prior to January 2001 claimant's home had not
experienced water problems. Claimant then contacted respondent and
was informed that a sewer line on Greenbrier Avenue had been filled
with concrete.

5. Employees of respondent and of Rainelle reconnected the
abandoned sewer line in February 2001.

6. Claimant has not had any more water problems since the
sewer line was reconnected.

7. Although respondent does not admit that its actions were
solely responsible for the claimant's property damages, it admits
that the work performed contributed to the damages, and therefore,
created a moral obligation on the part of respondent to provide
compensation to the claimant.

8. The parties are in agreement that $7,000.00 is a fair and
reasonable settlement for the property damages incurred by the
claimant.

The Court has reviewed the facts of the claim and finds that
respondent was negligent in its removal of the manhole and the
filling of the sewer line with concrete on Greenbrier Avenue in the
Town of Rainelle on the date of this incident; that respondent's
negligence proximately caused claimant to incur certain expenses;
and that the agreed settlement is fair and reasonable. Thus,
claimant may make a recovery for her sustained loss.

Accordingly, the Court is of the opinion to and does make an
award to claimant in the amount of $7,000.00.

Award of $7,000.00.
IN THE COURT OF CLAIMS OF THE STATE OF WEST VIRGINIA
CRAIG W. EVANS
VS.
DIVISION OF HIGHWAYS
(CC-01-120)

Claimant appeared pro se.

Xueyan Zhang, Attorney at Law, for respondent.
PER CURIAM:



Claimant brought this action for damage to his1994 Ford Escort
which occurred when he was traveling across a bridge on Parsons
Branch Road in Wayne County and the vehicle struck a large drop off
on the bridge. Respondent was responsible at all times herein for
the maintenance of Parsons Branch Road. The Court is of the
opinion to make an award in this claim for the reasons stated more
fully below.

The incident giving rise to this claim occurred on December 7,
2000, at 1:30 a.m., when claimant Craig Evans was on his way home
from work in Fort Gay. The weather and road conditions were
unremarkable and there was very little traffic at that time of
night. Mr. Evans described Parsons Branch Road as a narrow,
single-lane blacktop road. He normally does not take this route
home so he had not driven this road during the previous few weeks.
However, this route is a little shorter and that was the reason he
decided to use it on this occasion. Mr. Evans stated that he was
traveling thirty-five miles-per-hour. As he approached the small
bridge at issue, he saw no warning signs and he proceeded across
the bridge as he normally would. Suddenly, as he neared the end of
the bridge, he felt a bump and heard a strange noise. He kept
driving until he reached the top of a hill where the vehicle
stalled out. This was approximately two-tenths of a mile from
where the incident occurred. Fortunately, Mr. Evans was close to
his home and he was able to walk there safely. The next morning he
noticed that his vehicle's oil pan was busted and that the engine
was destroyed. Further, the front fender was bent and the front
bumper was cracked. Claimant's vehicle also sustained damage to a
headlight assembly and a park lamp. Claimant submitted an estimate
in the amount of $1,632.44 which represented the cost to have all
damages repaired except for the engine. He testified that he had
a new engine put in at a cost of $750.00. According to Mr. Evans,
he had purchased the vehicle six months prior to this incident for
$900.00. Claimant went back to the scene of the incident where he
observed oil strung out on the road beginning at the drop-off and
going up the road approximately fifty yards. He is certain that
this was oil from his vehicle. Mr. Evans estimated the drop-off at
the edge of the bridge to be approximately six inches. He also
noted that respondent had been working on the bridge recently. He
called respondent to report the incident and the condition of the
bridge.

Claimant contends that respondent was negligent in its
maintenance of the bridge and for failing to warn the traveling
public of a hazardous condition.

Geoffrey Adkins, respondent's storekeeper in Wayne County,
testified that he is familiar with the portion of road at issue. He testified that he was not aware of any hazards on the Parsons
Branch bridge prior to this incident. He found out about the
claimant's incident later in the day of December 7, 2000. He went
to the scene and determined that repairs needed to be made
immediately. He submitted into evidence a DOT-12 which indicates
that a problem was found on the bridge. It also indicates the
inventory and manpower used to make the repairs, which involved
using a large dump truck to fill the drop-off with cold-mix for a
safer transition. Mr. Adkins testified that another crew had been
working on the bridge six or seven days prior to this incident.
They had left the portion of the bridge where the surface of the
bridge starts to meet the road at least six inches too low. There
should have been a smooth transition from the bridge back onto the
road. However, respondent's employees had failed to fill in the
wooden surface of the bridge with blacktop to make it level with
the road. Finally, Mr. Adkins also stated that there were no
warning signs, barrels, or cones in place to give oncoming traffic
notice of the hazard.

The Court is of the opinion that respondent had notice of the
drop-off between the bridge surface and the road. Claimant's
photographs admitted into the evidence for this claim clearly
demonstrate the severity of this drop-off. Respondent had just
made repairs to the bridge less than a week prior to this incident
and yet this drop-off continued to be there. The Court has
determined that respondent had a reasonable amount of time to take
corrective actions, but failed to do so. Chapman v. Dept. of
Highways 16 Ct. Cl. 103 (1986); Pritt v. Dept. of Highways, 16 Ct.
Cl. 8 (1985). Respondent knew or should have known that the
condition of this bridge presented a very serious hazard to the
traveling public. Thus, claimant may make a recovery for the
damages to his vehicle.

The Court has reviewed the documents and claimant's testimony
regarding the damages to his vehicle. The damages exceed the value
of the vehicle in this claim; therefore, the Court considers the
value based upon the purchase price of the vehicle. In this
instance, any recovery will be limited to the amount paid by
claimant for the vehicle.
Accordingly, the Court makes an award in this claim in the
amount of $900.00 which the Court has determined to be the fair and
reasonable value of the vehicle at the time of the incident.

Award of $900.00.

CC-01-120
IN THE COURT OF CLAIMS OF THE STATE OF WEST VIRGINIA
NANCY A. STOUT
VS.
DIVISION OF HIGHWAYS
(CC-01-138)

William C. Garrett, Attorney at Law, for claimant.

Andrew F. Tarr, Attorney at Law, for respondent.
PER CURIAM:

Claimant Nancy A. Stout brought this action for personal
injuries and property damage to her 1992 Chevrolet truck which
occurred when her vehicle slid on ice and struck a hillside.
Claimant was traveling north on Route 20 in Webster County when
the incident occurred. This portion of road is maintained by
respondent in Webster County. The Court is of the opinion to deny
this claim for the reasons set forth below.

The incident giving rise to this claim occurred on December
15, 2000, at approximately 8:30 a.m. Claimant was driving home
from her place of employment. She works the night shift from 12:00
midnight until 8:00 a.m. She lives in Diana which is north of
Webster Springs, and on the date of this incident, she was working
in Bolair which is south of Webster Springs. Route 20 proceeds
through Bolair, Webster Springs, and Diana. Claimant described the
road conditions that morning as otherwise good and the weather was
clear. The temperature was approximately 32 degrees. She was
traveling down a portion of Route 20 known as McGuire Mountain and
was approaching a right-hand curve near an overlook. As she drove
into the curve, she testified that her vehicle slid on a patch of
"black ice" and then slammed into the mountainside. Ms. Stout
testified that all she recalls is losing control of the vehicle and
seeing the hillside coming at her. The next thing she knew was
that someone was pulling her truck door open to help her. She was
taken by ambulance to Webster Springs Memorial Hospital where she
was treated and released. She suffered a large cut to her head, an
injury to her leg causing heavy swelling, and serious bruising
under her right arm and her neck.

Claimant alleges that respondent failed to maintain properly
a ditch or culvert that had stopped up causing water to overflow
onto the road and freeze creating a hazardous condition known as
"black ice" which it knew or should have known existed. The total
damage to the vehicle was $3,849.00. However, claimant is limited
to the amount of her insurance deductible of $500.00. Claimant also incurred medical expenses in the amount of $1,519.34, all of
which were covered by her insurance except for $40.00 she paid
out-of-pocket.

Respondent asserts that it did not have notice of ice or water
on the road at the location of this incident, and that as soon as
it was made aware of the condition, the proper treatment was
provided.

Claimant testified that she drove this section of Route 20
five days a week for the past three or four years and that she was
very familiar with it. Although she did not see water or ice on
the road at the time of this incident, she has seen water running
across the road at this location before. She testified that water
runs down the steep hillside and often times does not go into the
ditch, but instead runs out onto the road.

Testimony at the hearing established that this ditch has to be
"pulled" occasionally, but respondent could not state the last time
this had been done. Claimant also established that there are a few
culverts along the road near the location of this incident, which
also require periodic maintenance. Respondent was not able to
provide information as to the last time this was done either.
Jimmy Collins, County Maintenance Supervisor for respondent in
Webster County at the time of this incident, is responsible for the
maintenance of roads and highways in Webster County. This includes
the portion of Route 20 at issue in this claim. Mr. Collins
testified that Route 20 is a priority one road and that he is very
familiar with it including the portion at issue in this claim. He
described Route 20 as a two-lane, blacktopped highway with double
yellow lines and white lines on both edges. The speed limit on
Route 20 is 55 miles per hour, but there is a 45 mile per hour
advisory speed sign for the curve where this incident occurred.
Mr. Collins travels this portion of Route 20 on McGuire Mountain
everyday on his way to and from work. He testified that he drove
past the exact location of claimant's incident earlier that same
morning at approximately 7:05 a.m. and he did not notice anything
out of the ordinary. He did not see any water or ice on the
roadway. He stated that he arrived at work between 7:00 a.m and
7:15 a.m., as he routinely does. It is approximately ten minutes
from the site of this incident to Mr. Collins' office. According
to Mr. Collins, it was raining lightly that morning, and it had
rained lightly the night before. He testified that the temperature
was warming up that morning to approximately 32 degrees and that
there was a little fog. Mr. Collins was not aware of claimant's
accident until between 7:30 a.m. and 8:15 a.m., when the 911 Center
called his office. After receiving this telephone call, Mr.
Collins sent a truck to the area with a mixture of salt and cinders
to spread onto the road as a precautionary measure. Respondent
submitted into evidence a Snow Removal and Ice Control (SRIC) log
for December 15, 2000, which showed that it sent a truck to the
location of this incident with three tons of salt and cinder
mixture at 9:00 a.m. The log also showed the same truck returning to its duty station at 10:00 a.m.

It is a well established principle that the State is neither
an insurer nor a guarantor of the safety of motorists on its roads
and highways. Adkins v. Sims, 46 S.E.2d 811 (W.Va 1947). To hold
respondent liable, the claimant must establish by a preponderance
of the evidence that respondent had actual or constructive notice
of the defect in question and a reasonable amount of time to take
corrective action. Chapman v. Dept. of Highways 16 Ct. Cl. 103
(1986); Pritt v. Dept. of Highways, 16 Ct. Cl. 8 (1985).
Respondent cannot be expected or required to keep its highways
absolutely free of ice and snow at all times, and the presence of
an isolated patch on a highway during a winter month is normally
insufficient to charge the respondent with negligence. McDonald v.
Dept. of Highways, 13 Ct. Cl. (1979). However, respondent at all
times does owe a duty to travelers to exercise reasonable care and
diligence in the maintenance of highways. Lewis v. Dept. of
Highways, Ct. Cl. 136 (1986).

In the instant claim, claimant has been unable to establish
evidence of any negligence on the part of the respondent.
Respondent did not have prior notice that a hazardous condition
existed on Route 20 at the location of claimant's accident.
Respondent's employee had just passed the exact location of this
incident shortly before it occurred and he did not observe any
water or ice on the road. Further, as soon as respondent became
aware of a problem, it sent a crew and truck out to treat the road
and remedy the situation. After reviewing all of the evidence in
this claim, the Court is of the opinion and concludes that any ice
that may have formed on the road at the location of this incident
did so shortly before the incident, and further, that respondent
did not have notice of the formation of ice on the road surface or
a reasonable amount of time to make adequate repairs.

Therefore, in view of the foregoing, the Court is of the
opinion to and does deny this claim.

Claim disallowed.